Regina city council denies demolition request for site where Louis Riel's body was kept

The Burns Hanley Building is a heritage property at 1863 Cornwall St. where Louis Riel's body was briefly kept after his execution.

Council voted 9-1 to deny the demolition application for 1863 Cornwall St.

City council will decide whether to approve a demolition permit for the Burns Hanley Building in Regina's downtown. (Google Maps)

City council has rejected an application to demolish a downtown Reginabuildingwith a connection to Louis Riel.

At a meeting on Wednesday, councilvoted 9-1to deny an application todemolishthe Burns Hanley Building.

Coun. Terina Shaw of Ward 7 was the only dissenting vote.

The Burns Hanley Building sits on the site once occupied by St. Mary's Roman Catholic Church, which was built in 1883.

Some of the extensive damage recorded by JCK Engineering at the Burns Haley Building in 2019. (JCK Engineering/City of Regina)

The Burns Hanley Building was constructed on the site in 1912. The church that previously stood on the site was whereLouis Riel's bodywas briefly kept after the Mtis leader's execution in 1885, before it was sent to Winnipeg.

City staff initially recommended approving thedemolition application for 1863 Cornwall St., but that recommendationwas voted against by the Regina planning commission at an Oct. 6 meeting.

The committee recommended thatcouncil deny the demolition application and order Harvard Developments, the company that owns the property,to complete "at minimum"repairs necessary to stabilize the building and preserve itsfacade.

Council amendedthe recommendations, referringthe issue to the provincesHeritage Review Boardinstead of ordering Harvard Developmentto stabilize the building.

The review board will now decide about what can and should be done.

Coun. Bob Hawkins was one of the voices instrong support of protecting the building's facade.

That idea was supported by Jackie Schmidtof Heritage Regina, who spoke to council ahead of its vote.

Schmidt said she would accept the building's demolition due to the sad state of the structure as long as there wereefforts from the city and Harvard to keep the original facade.

"The facade of the building is what is protected and so we should put steel supports on that facade until such time as they come up with a plan as to what that looks like," Schmidt said.

The Burns Hanley Building is a designated heritage building in the city'sVictoria Park Heritage Conservation District.

Harvard applied for a permit to demolish the building in July 2021, citing its deteriorating condition.

The roof of the Burns Hanley Building is severely damaged. JCK Engineering noted in its report that vegetation is growing on the roof. (JCK Engineering/City of Regina)

A 2019 engineering report by JCK Engineering found the building had undergone years of sustained water damage due to a damage roof and broken pipes.

The report recommended$200,000 in repairs that would have helped to stabilizethe building.

No repairs were carried out.

Two years later, the same company inspected the building again and found that water damage was so severe, and the condition was so poor, that they were unable to inspect parts of the structure.

"The building is unsafe and should not be occupied for any reason," the JCKEngineering report concludes.

The fallen ceiling of the second floor of the Burns Hanley Building in Regina. (JCK Engineering/City of Regina)

Due to the extensive damage, the repair estimates have skyrocketed to$4.7 million.That includes structural repairs, shoring up walls, and removal of debris and hazardous material.

Organizations and councillors speaking in favour of preserving the buildingahead of Wednesday's voteraised concerns about how the building deterioratedand why repairs weren't carried out after the 2019 engineering report.

In a letter to members of city council, Heritage Regina implied theBurns Hanley Building is a "victim of demolition by neglect."

Organizations noted that the city could have used its powers under the Heritage Property Act to enforce required maintenance of municipal heritage properties.

Harvard's initial application did not have a proposed redevelopment plan, despite a city bylaw requiring one.

Instead, Harvard said itsinitial plan was to infill the basement of the demolished building, as it plans to acquire neighbouring propertiesand then develop a mixed-use highrise building.

City staff noted in its report that allowing the demolition could create a precedent for "allowing the neglect and deterioration of other designated buildings."