Saskatoon's Remai Modern Art Gallery behind schedule and over budget

The latest report to the city's executive committee on the Remai Modern Art Gallery says the project is over budget and behind schedule.

Ongoing revisions to interior blamed for overruns

Saskatoon's new art gallery is late and expensive. (Dan Zakreski/CBC)

The Remai Modern Art Gallery is behindschedule and over budget.

A report going to Saskatoon city council'sexecutive committee on Monday details what's happening at the showcase riverbank project.

According to the four-page update, corrections and clarifications to the internal drawings are to blame. The projected cost is now between $87.2 million and $88.4 million. Thatis $3.5 to $4.5 million higher than expected.

The gallery isnow forecast to open in 2017, not next year as projected.

"The change between what the contractor bid on the original drawings versus what the new design condition requires, has resulted in the contractor having to expend additional resources," the report states.

Cityadministration is expected to work on finding ways to cover the shortfall.

The next update will come before the end of the year.