Toronto councillors demanding answers from Metrolinx about Ontario Line transit project - Action News
Home WebMail Friday, November 22, 2024, 08:50 PM | Calgary | -11.3°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Toronto

Toronto councillors demanding answers from Metrolinx about Ontario Line transit project

Three Toronto city councillors are pushing for more insight and input into the massive Ontario Line transit project. They say the provincial agency charged with building the multi-billion dollar subway line is being too secretive.

Transit agency accused of secrecy surrounding 15-kilometre subway line through downtown

A map showing the subway stops for the Ontario Line.
The Ontario Line will be a 15-stop subway route that's slated to run almost 16 kilometres from the Ontario Science Centre to Ontario Place. (Metrolinx)

Three Toronto city councillors are pushing for more insight and input into the massive Ontario Line project, slamming theprovincial transit agency charged with building the multi-billion dollar subway line for being too secretive.

Ausma Malik, Chris Moise and Paula Fletcher received the backing of their colleagues on the Toronto and East York Community Council this week to create a sub-committee to dig into the project. The group will begin meeting next month and will receive formal updates from city staff and can hear deputations from community members.

Malik, who represents Ward 10, Spadina-Fort York,said they decided to form the sub-committee because as planning for the Ontario Line has proceeded, communitiesand the politicians representing them have been consistently left out of the process.

"Metrolinx and the provincial government have fallen short in terms of their community engagement, in terms of their responsibility to ensure that they're listening to local stakeholders," she said.

The 15.6-kilometre Ontario Line was announced by Premier Doug Ford in 2019. The routeis set to have 15 stations and run through the downtown core from Ontario Place in the west to the Ontario Science Centre in the east.

Its initial price was pegged at $10.9 billion. But inNovember, the province updated that estimate, revealing that because of supply chain issues and inflation the price taghas jumped to between $17 and $19 billion. Those figures don't include a number of costs, including the actual trains themselves or storage facilitiesfor them.

Constructionwas first projected to wrap in 2027. Asked Friday when the line is expected to be completed, Metrolinx would not say.

Metrolinx criticized forplan and communications

Critics have questionedMetrolinx'splanand have accused the provincial agencyof a lack of communication and poor consultation withcommunities that are affected. Metrolinxalso landed in legal hot water whena number of groups challenged its plan to cut down trees on the historic grounds of Osgoode Hall to build a station on the line.

Moise, who represents Ward 13, Toronto Centre, said his constituents andthose of the other two councillorsare the most impacted by construction on the project. And while the committee cannot compel Metrolinx to take part in its work, good planning comes from rigorous community consultation, he said.

"We are in dire need of more transit," he said."I'm very much in support of the Ontario Line. But weknow that Metrolinx have not always been forthright and forthcoming."

Councillors Chris Moise and Ausma Malik say they pushed to form a sub-committee at City Hall to get answers on the multi-billion dollar Ontario Line. They say their communities will be deeply impacted by the subway construction project and the provincial agencies in charge of building it are not being transparent enough about their work.
Councillors Chris Moise and Ausma Malik say they pushed to form a sub-committee at city hall to get answers on the multi-billion dollar Ontario Line. They say their communities will be deeply impacted by the subway construction project and they say the provincial agencies in charge of building it are not being transparent. (CBC)

Fletcher, who represents Ward 14, Toronto-Danforth, said Metrolinx has been communicating its plan"in chunks," which has impeded local councillors' ability to viewthe scope of the project. The committee will allow councillors to take a longer view of the work, she said.

"Right now, we're just seeing the trees we really need to see the forest," she said. "And I think this will give a very clear overview of the entire area."

Metrolinx 'too secretive,' Matlow says

Coun. Josh Matlow, who represents Ward 12, Toronto-St. Paul's,said lessons fromMetrolinx's delayed Eglinton Crosstown LRT must be applied to the Ontario Line and hesupports forming the sub-committee.

"They're too secretive," he said of Metrolinx.

"The sooner there is more accountability and transparency with Metrolinx, the better transit will be built. And we're just not accepting that Metrolinx can just run roughshod over the people of Toronto without having a place where we are demanding answers."

A construction site.
Construction of the Eglinton Crosstown LRT is seen here still ongoing at Yonge Street and Eglinton Avenue in December. The project has been delayed three times. Coun. Josh Matlow says Metrolinx needs to apply the lessons learned from the controversial project to the Ontario Line. (Angelina King/CBC)

Metrolinx said in a statement that it regularly updates and seeks feedback from communities across Toronto on the Ontario Line.

"We continue to work closely with our partners at the City of Toronto, meeting on a weekly basis, as we deliver this important project," said the agency's media relations department.

"We have been coordinating plans with city staff and we look forward to continued collaboration as we move this project forward."

Canada's 'most expensive' subway?

Stephen Wickens, a Toronto freelance researcher and journalist who specializes intransit issues,said the Ontario Line has been desperately needed for at least four decades, so he has been willing to overlook some flaws with the current plan. But he saidhe's increasinglyworried about the approach to designingthe project and the lack of communication.

"The secrecy that goes with Metrolinx's approach of not providing crucial information to anybody who might ask good questions is a problem," he said.

"They like to use this excuse that it's commercially sensitive material. It's not serving them and I don't think it's serving the people of Ontario."

A sign is pictured near Osgoode Hall as Metrolinx begins the removal of centuries-old trees early Saturday morning.
A sign is pictured near Osgoode Hall as Metrolinx began cutting down centuries-old trees. The provincial transit agency has been fighting several attempts to stop the removal of the trees in court. (CBC)

Wickens, who in 2020 penned a report on the spiraling costs of subway projects for the Residential and Civil Construction Alliance of Ontario, saysthe project could be on track to break a record when it comes to costs..

"This Ontario Line was supposed to have been a way of getting better value for the public," he said.

"It looks to me like, and certainly from the early contracts that have been signed, that this is going to be the most expensive subway ever built in this country."

"And I'd be shocked if it's ready by 2030," he added.

The committee will meet next month to develop terms of reference for its work headed into the spring and could hear from the city's Transit Expansion Office on the status of the line.

That update is also expected to include details about the pedestrian and traffic management plans and to identify places where the city and residents can be involved in the project's development.

"We're hoping that Metrolinx listens," Malik said.

"And I believe that it's in their best interest to be able to come to the table and for the provincial government to step up."