In 'extraordinary step,' company building Eglinton Crosstown hits province with lawsuit - Action News
Home WebMail Monday, November 11, 2024, 05:05 AM | Calgary | -1.6°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Toronto

In 'extraordinary step,' company building Eglinton Crosstown hits province with lawsuit

Crosslinx says it's facing more than $134 million in unforeseen costs due to COVID-19. But Metrolinx is firing back, saying company was behind on its work long before pandemic struck.

Transit megaproject not set to open until well into 2022

The company building Toronto's Eglinton Crosstown megaproject has filed a lawsuit over what it says are more than $134 million worth of added costs driven by the COVID-19 pandemic. (Michael Wilson/CBC)

Crosslinx, the company building Toronto's Eglinton Crosstown LRT, is suing Metrolinx and Infrastructure Ontario as it faces upwards of $134million in unexpected costs it says were caused by the COVID-19 pandemic.

Crosslinx says it performed an analysis that showed the first wave of the pandemic added $134 million to the megaproject's costs, and warned a second wave could drive that price tag even higher.

In a news release, Crosslinx spokesperson Kristin Jenkins called the move an "extraordinary step" and attacked the two provincial agencies for their "refusal to declare COVID-19 an emergency and recognize the significant impacts the global pandemic is having on Eglinton Crosstown LRT construction."

Metrolinx is already firing back, saying Crosslinx was behind schedule before the pandemic hit.

Crosslinx, the statement said,"has consistently failed, month after month, for two years, to achieve their production rates," notingsince 2018, only 72 per cent of planned work has been completed.

It added there's a dispute resolution process in place and urged Crosslinx to use that, rather than the courts to solve its issues.

"Rather than legal action, we need CTS to focus on what is most important getting the Eglinton project completed,"Metrolinx said.

Crosslinx has sued Metrolinx before, in 2018, over the megaproject's timeline. That lawsuit was settled.

Costs driven by sick calls, supply chain woes

It blames the soaring costs on a range of factors, including:

  • Implementing provincially-mandated COVID-19 health and safety protocols
  • High rates of "COVID-related absenteeism"
  • Supply chain problems

Crosslinx added its subcontractors are facing similar problems, and that it has received hundreds of notices requesting relief in the form of more time or more money.

The company said in a news release it is still dedicated to completing the transit line, the opening of which is now not expected until well into 2022, according to Metrolinx. The more than $5 billion project was originally slated to open in 2020.

CBC Toronto is chasing reaction from Infrastructure Ontario.

You can read the full legal filing in the PDF below:

Mobile users: View the document
(PDF KB)
(Text KB)
CBC is not responsible for 3rd party content