Should Toronto hit the brakes on the $1B Gardiner East project? A city hall debate could be coming

A Toronto city councillor wants an update on the costs of the Gardiner East project to see if there is an off-ramp for the costly restoration work on the aging elevated expressway.

Key committee set to dig into costs involved in refurbishing segment of elevated expressway

Toronto city councillors will review the costs of the Gardiner East project at an upcoming Infrastructure Committee meeting. This comes after a slim majority voted at this week's city council to dig into the details of the $1.053 billion project approved in 2016.
Toronto city councillors will review the costs of the Gardiner East project at an upcoming Infrastructure Committee meeting. This comes after a slim majority voted to dig into the details of the $1.053 billion project. (Tony Smyth/CBC)

A Toronto city councillor wants an update on the costs of the Gardiner East project to see if there's an off-ramp the city can taketo avoid thecostly restoration workon the aging elevated expressway.

Coun. Josh Matlow pushed the issue onto a key city committee agenda in a bid to re-open debate on the controversial project, which council voted onback in 2016. At that time, councillors decidedto spend just over$1 billionon the "hybrid" option, whichretains the eastern portion of the expressway, moving it farther northwhile tearing down a ramp over Logan Avenue.

"Rebuilding new sections of an elevated expressway takes us away from all of our other priorities," Matlowsaid Friday.

The choice was made instead of tearing down a 1.7-kilometre sectionof the Gardiner east of Jarvis Street and replacing it with a surface-level boulevard for less than half the cost.

Matlow, who represents Ward 12, Toronto-St. Paul's,said council needs an update on the progress and the costof the project to date. That might lead to the city re-considering the decision altogether, he said.

"It's not good urban planning. It's not a good use of money. But especially in the context of a finite budget that has a shortfall of hundreds of millions of dollars, I think it's just really reckless."

Councillor Josh Matlow has led the push to review the Gardiner East costs, saying it's time to see if there's an off-ramp for the expensive project.
Coun. Josh Matlow has led the push to review the Gardiner East costs, saying it's time to see if there's an off-ramp for the expensive project. (Michael Wilson/CBC)

City staff say approximately $500 million earmarked forthe project has been spent or committed to in contracts. The city said Fridayan additional $770million is set aside in the city's 10-year capital budget for work still planned to begin in 2026.

The projectrepresents approximately 14 per cent of the city's overall 10-year capital plan, Stephen Conforti, the executive director of the city'sFinancial Planning Division,said in a statement.

Approximately $60 million is set aside to be spent on the project in 2023, which is 14 per cent of the city transportation department's $435-million capital budget.

The work already completed on the project cost $340 million and includesrealignment of both the expressway from Cherry Street to the Don Valley Parkway and Lake Shore Boulevard, and new on and off ramps east of Cherry Street.

But city staff warned this week thatthe cost of the other work on Lake Shore Boulevard needs updated costing.That includes"public realm" construction, utility relocations, and electrical work. Staff could provideupdated projections for thatas soon as next month.

"The estimate did not account for the significant inflation that's being experienced onconstruction projects," City Manager Paul Johnson warned in a reportto council this week.

This comes at a time when the COVID-19 pandemic has driven up the city's budget gap to $1.5 billion for combinedcosts in2022 and 2023.

It's likely 'costs haveescalated': Fletcher

Coun.Paula Fletcher, whose ward is home to part of the project, said she's eager to hear a cost update, but is predicting an increase.

"We're going to find out that the costs have escalated because the original numbers were in 2013 dollars, so here we are in 2023," she said. "And I think anybody knows that when you renovate an old anything, you're going to find a few problems."

The Gardiner Expressway was built in segments between 1955 and 1966. When council adopted the "hybrid" plan, which includes rehabilitating aging portions of the expressway, staff said it was an urgent matter because the roadway was reaching the end of its service life.

A woman stands in front of a microphone answering questions from a reporter.
Coun. Paula Fletcher says it's likely 'costs have escalated' for the Gardiner East and she's calling for a 'very forensic' review of the project. (Grant Linton/CBC)

But Fletcher cautionedthat changing course will not be simple because multiple projects in the Port Lands are now linked to on-going Gardiner East work.

"The projects look like they're all nested together," she said. "I just know that we'll want to know some numbers It might turn out it wasn't the best decision financially for the small number of commuters that it was set to save time for."

In 2016, proponents of keeping the Gardiner East said its removal would create congestion and hurt Toronto's economy. The city's traffic modelling predicted full removal breaking the link between the Gardiner and Don Valley Parkway would add between three and five minutes tocommutes.

But Fletcher said traffic studies have also shown that most drivers don't use thatsection of the highway daily.

"I think we need to be very forensic and not emotional while we're looking at this and come up with what could be a plan," she said.

'An inflationary moment'

MattiSiemiatycki, the director of the Infrastructure Institute at the University of Toronto, said he expects costs forthe project have jumped.

"There's a saying with construction that the best time to have done it was always yesterday," Siemiatycki said.

"We are in an inflationary moment and construction has not been spared and the costs are rising."

Siemiatycki said he's not surprised to see the "hot-button" issue of the Gardiner raised again. Some factors surrounding the debate remain the same as in 2016, like the city's housing and climate challenges, and moving cars and goods through downtown, he said.

One of the proposals for the East Gardiner was an eight-lane at-grade urban boulevard lined with retail options, trees and sidewalks. City council rejected it in favour of the plan to divert the easternmost section of the elevated expressway northward. (Waterfront Toronto)

But the city's fiscal picture has darkened significantly, Siemiatyckisaid.

"You're starting to see people talking about the city feeling shabby and I think that might be contributing to why this project is in the spotlight again," he said.

"It is such a large part of the capital budget, the financial dynamics have changed."

Mayor's office warns of $340M in 'throwaway costs'

Mayor John Tory repeatedly said during the election last year that he would not revisit the decision to go ahead withthe project. His office said Friday that changing course would result in "throwaway costs" of $340 million.

"This project is well underway one section, essentially half has already been rebuilt and the on/off Logan ramps have already been removed," Tory spokesperson Taylor Deasley said in a statement.

Altering the plan is expected to save no money, and could possibly cost the city more money, she added.

"Councillors pushing this myth conveniently ignore that there is still 16 kilometres of expressway ... that needs to be kept in a state of good repair."