Toronto to replace 'vintage' water mains, upgrade Jarvis Street in $2.3M project

City crews are expected to begin replacing two "vintage" water mains and reconstructing part of the road on Jarvis Street this week in a project that will cost $2.3 million, the city's chief engineer says.

Work is set to begin this week and will continue until the end of October, the city says

Part of a vintage water main. This cast iron pipe, 400 mm in diameter and constructed in 1905, was taken from Queen Street East. The image is from a Toronto Water study. (Toronto Water)

City crews are set to replace two "vintage" water mains and reconstruct part of the roadway on Jarvis Street this week as part of a $2.3 million project, Toronto's chief engineer says.

The old water mains, situated between Dundas Street East and Queen Street East, aremore than a century old, according to Michael D'Andrea, executive director of the city's engineering and construction service.

Crews will replace both pipes with a new, larger diameter PVC water main to improvewater service in the area, he said. Road crewswill also bring that stretch of Jarvis Street up to a state of good repair.

"It is a big project," D'Andrea told CBC Toronto.

The work ispart of a wider $720-million plan to maintain and improve infrastructure in Toronto. Itisan attempt by the city to "stay ahead of the curve" in the hopeof preventingwater service disruptions, water main breaksand resulting damage to roads that could affect traffic, businesses and residents, he said.

The upgrades are also necessary to support future growth in the downtown core, he added.

Michael D'Andrea, chief engineer for the city, said the project will undoubtedly cause disruptions for traffic and pedestrians, but new technology could help ease delays. (CBC)

Toronto Water and Toronto Transportation Services, he said, are working together to ensure the project creates the least inconvenience possible.

"In Jarvis Street, it is truly an integrated project," D'Andrea said.

The combined effort will be carried out in two phases to minimize disruptions to residents and traffic.

"At our end, it's integrating those needs as one single construction contract, rather than going in, replacing the water main, then sometime latercoming in and reconstructing the road," he said.

If all goes as planned, the water mains be will be replaced by early October and the subsequent roadwork completed by the end of October.

A city worker operates a road cutter. Road replacement is a major part of the Jarvis Street project. (Michael Charles Cole/CBC)

One northbound lane and one southbound lane of JarvisStreet between Dundas and Queen streets will be open to traffic during the construction period. However drivers and cyclists will be urged to use either Church or Sherbournestreetto travel to the downtown core.

Some curbs and driveway entrances will be dug up and replaced, but there will be pedestrian access, according to the city.

"Smart" traffic signs placed at Adelaide and Queen streets will provide road users updated estimates of how long it will take to travel through the work zone northbound to GerrardStreet E. The new signs are part of Toronto'ssmart work zone pilot, the city said in a news release.

It will allow officials to monitorconditions in real time and make any necessary changes to traffic signal timing to help reduce delays.

Replacing aging infrastructure 'critically important'

While work on Jarvis is ongoing, crews will also replacean aging water main on Gloucester Street. The street will be temporarily closed at YongeStreet and a stretch between Yonge and Jarviswill be reduced to a single lane.

The decision to replace any individual water main is based on age, condition and the number of breaks it has seen in the past, D'Andrea said.The city is trying to "get ahead of the curve" and replace crumbling infrastructure before"it begins to impact us quite significantly," he continued.

There are about 1,400 water main breaks per year in Toronto, he explained.Replacing those at the end of their service life is "critically important" moving forward, D'Andreaadded.

Most of the work on the JarvisStreet will take place Monday to Friday, from 7 a.m. to 11 p.m., with some work on weekends and overnight as needed.