Windsorites chose 'campus' option for new city hall

Windsorites have chosen the "campus" option as the new design for a new city hall building.

The city asked the people and the people answered.

Windsorites have chosen the "campus" option as the new design for a new city hall building.

People had a chance to weight in online or by ballot at the current city hall.

They had two options to choose from: the "gateway" and the "campus."

Online 1,114 people voted, 783 voted for the campus design and 331 for the gateway.

By ballot 82 people voted, with 54 people making the campus box, while 28 for gateway.

The cost of both buildings was estimated between $22.5 million to $24.4 million.

The entire project from concept to move-in ready is estimated at $35.5 million.

The construction phase of the project is scheduled from Nov. 2015 to Dec. 2017, with a move-in date of April 2018.