Ottawa gives pipeline regulator 22 weeks to review Trans Mountain expansion project - Action News
Home WebMail Friday, November 22, 2024, 06:22 PM | Calgary | -11.5°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Politics

Ottawa gives pipeline regulator 22 weeks to review Trans Mountain expansion project

The Liberal government is instructing the federal pipeline regulator to review the Trans Mountain pipeline expansion to consider the project's impact on the marine environment.

Federal government says process to consult with Indigenous groups will come next

The twinning of the 1,150-kilometre Trans Mountain pipeline would nearly triple its capacity to an estimated 890,000 barrels a day and increase traffic off B.C.s coast from approximately five tankers to 34 tankers a month. (Dennis Owen/Reuters)

The Liberal government is instructing the federal pipeline regulator to review the Trans Mountain pipeline expansion to consider the project's impact on the marine environment.

Natural Resources Minister AmarjeetSohisaid Friday the National Energy Board will have 22 weeks to hear from Canadians and report back to government.

Sohiannounced details of the government's next steps during a news conference in Halifax with Fisheries Minister Jonathan Wilkinson. He called the new NEB reviewa"very important step forward" but said word on new consultations with Indigenous peoplewould come at a later date.

Sohiinsisted the expansion project is an investment in Canada's future, but that it must move aheadin the "right way."

As more consultationwith Indigenous peopleis critical to advancing the project, he said he could not put a timeline on when construction could actually begin again.

"We are focused on getting this project right. We want to make sure that everything we do enables us to move forward on this project, which is very importantproject for Canada's economy,"said Sohi.

The minister said the government will outline plans for further consultation with Indigenous peoplein due course.

Last month, the Federal Court of Appeal quashed the approval of the $7.4-billion pipeline project that would nearly triple the flow of oil from Alberta's oilsands to the West Coast.

The court said Canada's efforts to meaningfully consult with Indigenous people, as required by law, fell short, and criticized the lack of attention given to how increased tanker traffic off the coast of British Columbia would affect the environment.

Sohisaid thisreview will consider the impact of increased tanker traffic onthe resident killer whale population.

Addressing killer whale population

The government will present the NEB with information about recent actions to protect species at risk and to implement the $1.5-billion Oceans Protection Plan.

It also willappoint aspecial marine technical adviser to the NEB to ensure the regulatorhas the "expertise and capacity" to givethe best advice to the government.

The next stage of the project reboot will be toaddress the court's concerns about consultation with Indigenous people, and that will be announced shortly, he added.

"Our government is committed to making sure that we engage with Indigenous peoples in a meaningful, two-way dialogueand explore opportunities for us to work together."

Sohisaid the government has not yet made a decision on whether to appealthe Federal Court of Appeal ruling to the Supreme Court of Canada.

NEB 'confident' with timeline

In a statement issued today, the NEB saidit's "confident" it can complete thework within the required timeline, and will provide more information about next steps "in the coming days."

Alberta Premier Rachel Notley said today she did not want to name a date when reconstruction must beginbecause putting a limit on consultation with Indigenous peoplewould undermine the credibility of the process and give opponents ammunition to file a legal challenge.

She said it's more important to have a clear process that people can understand and rely on, and warned that there should not be any slippage in the 22-week timeline for the NEB review.

Alberta will keep the federal government's "feet to the fire" to ensure that deadline is met, Notley said.

"At the end of the day, what matters most to our government, to workers, to employers, to investors ... is that there's a timeline that is credible that people can make plans on the basis of," she said. "That is what we need to have in place."

B.C. impact

B.C. Premier John Horgansaid it's good news that there will be a review of the project's impact on the marine environment, but added it'stoo early to say if the process will be adequate.

"Our marine environment is critically important to our economy," he said.

"It's important to the very being of British Columbia and we had said all along that the federal government,the previous government and the current government, did not adequately measure the consequences of a diluted bitumen spill. This is an opportunity to do that."

Conservative natural resources critic Shannon Stubbsaccused the Liberals of dragging their feet and said today's announcement offers no assurance the pipeline expansion will ever get built.Three weeks after the federal appeal court's ruling, she said, the government has failed to provide a clear, comprehensive and concrete plan to ensure the project moves forward.

"Today, there are no timelines for shovels in the ground," she said."There is no timeline for completion, no timeline for jobs. Getting the Trans Mountain expansion built should be this government's top priority, but instead, the Liberals have spent $4.5 billion of Canadian taxpayers' money that will be invested in the U.S."

Stubbs said that, if elected, the Conservatives would bring pipeline proponents that have been vetoed back to the table, and create the conditions to ensure energy projects get off the ground.

'Definition of insanity'

NDPMP Nathan Cullen said the Liberals are prolonging a process which already has determined that increased tanker traffic will harm endangered killer whales.

"Doing the same thing and expecting different resultsis the definition of insanity," he said.

Cullen also questioned the government's commitment to hearing from, and acting on, the concerns ofIndigenous people.

"You can't have meaningful consultations if you've already made up your minds," he said.

"For them to go to Indigenous leaders in B.C. and say, 'We'dnow like your opinion' is the opposite of meaningful. It's tokenism, it's paternalistic."

Calls to kill project

The Union of B.C. Indian Chiefs (UBCIC) issued a statement calling on Prime Minister Justin Trudeau to kill the"ill-conceived and ill-fated project"and cancel the directive to reassess it.

"The Trudeau government's fanatical determination to build this disastrous pipeline and tanker project is boorish and disheartening," said Grand Chief Stewart Phillip, president of the UBCIC.

"It is clear that Indigenous and non-Indigenous peoples alike do not want this project built. Instead of continuing to waste more money, timeand resources on this aberration, Mr. Trudeau needs to accept the public's rejection, as reified by the wisdom of the courts, to reject the project altogether."

Other Indigenous groups, including some whose communities are located along the proposed pipeline route, are in favour of the development.