Home | WebMail | Register or Login

      Calgary | Regions | Local Traffic Report | Advertise on Action News | Contact

Login

Login

Please fill in your credentials to login.

Don't have an account? Register Sign up now.

North

Cost of cleaning up Yellowknife's Giant Mine now pegged at $4.38B, up from $1B

The previous cost estimate of $1 billion was developed in 2010, and that was a 'pure construction cost estimate,' says the deputy director of the Giant Mine Remediation Project.

New price tag is more than four times the initial estimate

A building with huge round stack on the ends sits on top of a hill with trees and orange dirt in the foreground.
The previous cost estimate of $1 billion was developed in 2010, and that was a 'pure construction cost estimate,' said Natalie Plato, deputy director of the Giant Mine Remediation project. Plato revealed the new $4.38-billion price tag on Thursday. (Chantal Dubuc/CBC)

The remediation of Giant Mine in Yellowknife is expected to cost the federal government $4.38 billion more than four times the initial estimate.

This makesthe cleanup of the former gold mine the most expensive remediation project in Canada's Northern Abandoned Mine Reclamation Program.

The previous cost estimate of $1 billion was developed in 2010, and that was a "pure construction cost estimate," Natalie Plato, deputy director of the Giant Mine Remediation Project, said Thursday,after revealing the new estimate.

Theproject has changed significantly since then, she said.

The remediation of Giant Mine is an extraordinarily complicated undertaking that includes containing237,000 tonnes of highly toxic arsenic trioxide dust deep underground.

When asked why the initial estimate was so much lower than today's, Plato said"when we went in, we went in wanting to get this project done, and we didn't do extensive consultation."

Plato, who said she wasn't involved at the project's outset, said they got referred to an environmental assessment and heard Yellowknife-area residents wanted more consultation, more involvement and more work done on the site.

"All of those things do come at a cost," she said.

A woman with a safety vest and yellow hard hat. She's outside.
Natalie Plato is the deputy director of the Giant Mine Remediation Project. Plato said a lot has changed since the initial cost estimate for the remediation project, including extensions to the project's scope and timeline. (Liny Lamberink/CBC)

$710M spent on project to date, says Plato

The remediation project's budget is not publicly available.

Plato said that's because their work is done through competitive bids and requests for proposals, and "those are protected so contractors don't get our costs, because that can compromise the contracting process."

The $4.38-billion estimate was drawn up by the remediation project team and approved by the Treasury Board of Canada. It includes all the project's costs from 2005 until 2038, when remediation is set to finish.

Plato said the updated price tag takes into account contingency (i.e. potential unforeseen expenses), inflation, GST values and the $710 million that has been spent on the remediation project so far.

Plato said a lot has changed since the initial cleanup cost came out.

For one thing, the environmental assessment led to 26 legally binding measures meant to minimize the negative environmental impacts of the project and resulting public concerns.

One of those measures was the creation of the six-person Giant Mine Oversight Board.

Another was the multi-year health-effects monitoring program,which tests people in the nearby communities of Yellowknife, Ndilo and Dettah for arsenic concentrations in their urine and toenails.

Through consultations, the team heardnortherners wanted northerners to benefit from the remediation project, Plato said.

To make sure local firms and people could bid on, and carry out, work at the mine site, the project team extended its schedule by nine years "to ensure that the work is right-size for northerners to participate," said Plato. "So that also comes at a cost."

The remediation project reports that to date, $331 million in contracts 51 per cent of the total value of contracts it's awarded have gone to Indigenous contractors.

Rows of shipping containers sit on top of each other in the distance on a landscape that is sand and dirt. There is some machine that sits in the front.
Here are rows and rows of about 360 shipping containers, filled with the toxic remnants of the roaster building, which used to separate the gold from the rocks. Though remediation is set to wrap up in 2038, the mine will need maintenance in perpetuity. Plato said the federal government committed to looking after the mine site for 100 years. (Priscilla Hwang/CBC)

Consultations led to changes in the scope of the project as well, said Plato.

The team had originally planned to leave eight pits open, but after hearing concerns about health, safety andunderground flooding in the mine, the team decided to fill the pits.

They also designed Baker Creek to accommodate a major flood. Baker Creek carries waterfrom tailings ponds, whichis treated so it meets or exceeds regulatory requirements,into Yellowknife Bay.

A benefit agreement with the Yellowknives Dene First Nation also wasn't included in the initial remediation plan, said Plato. That agreement is valued at $2 million a year for the life of the project.

She said the benefit agreement includes money for training and positions for Yellowknives Dene First Nation members.

"Jeez, there's so many other things, as well," said Plato, when listing off factors that drove up costs.

A pond in the fall with a sign that says
A settling pond at the Giant Mine site on Sept. 21, 2022. 'A lot more work that needs to be done, but I think we're in a way better place than we were 10, 15 years ago,' said Yellowknife MLA Kevin O'Reily. (Liny Lamberink/CBC)

Kevin O'Reilly, MLA for Frame Lake in Yellowknife, said he wasn't surprised to see the costs balloon.

"Given the mess that the government allowed to happen there, these are costs that are required to try to protect the public from the health effects of arsenic that was generated at the mine site," he said.

"So yeah, I think we have to spend this money and I think doing it right is very important."

O'Reillysaid long-term monitoring and maintenance of the mine site will surely wrack up costs decades and even centuries into the future. For example, the government will need to make sure the arsenic stays contained,properly store records, and communicatewhat happened at the mine to future generations.

"A lot more work that needs to be done, but I think we're in a way better place than we were 10, 15years ago," he said, "but I'd rather spend that money on almost anything else."

Feds to cover vast majority of costs

The federal government will cover the vast majority of the remediation costs. Plato said the Northwest Territories government is pitching in about $20 million.

She saidpart of the territory's contribution included rerouting the Ingraham Trail, which used to run right through the mine.

CBC attempted to verify the territory's contribution with the N.W.T. government, but did not get a response on Thursday.

David Livingstone, chair of the Giant Mine Oversight Board, wasn't available for an interview but said in an emailed statement that, "the Giant Mine Oversight Board was informed only recently of the new estimates and will reserve comment until it has received and reviewed the relevant background information from the Project Team."

Though remediation is set to wrap up in 2038, the mine will need maintenance in perpetuity.

Plato said the federal government committed to looking after the mine site for 100 years. This means the remediation project's funding is protected, no matter who's in government.

Responsibility for Giant Mine was foisted onto the federal government after former owner Royal Oak Mines Inc. went into receivership in 1999.

According to Plato, the federal government has learned from the disastrous outcome.

"We've changed how we permit mines now, and we do require security, and we do require progressive reclamation," she said.

"We are doing better and this should never happen again."

Neither Chief Edward Sangris of Dettahnor Chief Fred Sangris of Ndilo were available for an interview on Thursday.