Tuktoyaktuk highway construction behind schedule

Construction has wrapped up for the season on the Inuvik to Tuktoyaktuk highway, 11 kilometres short of its 40 kilometre target.

Larry Purcka talks Tuk road construction

10 years ago
Duration 1:59
Larry Purcka talks Tuk road construction

Construction has wrapped up for the season on the Inuvik to Tuktoyaktuk highway, 11 kilometres short of its 40 kilometre target.

On the Inuvik side, crews built 13 kilometres of road while Tuktoyaktuk crews built 16 kilometres. Despite the progress both missed their construction targets. Each side was supposed to build 20 kilometres of road.

Larry Purcka, senior program manager for the N.W.T.'sDepartment of Transportation, says thethis season'sshortfall isn't a problem.

"Are we concerned?No," he said. "Has the contractor got a good plan, is prepared to catch up next year? They're working on it and we believe that next year is going to be very successful for them."

A late start is one of reasons the highway is behind schedule. Contractors weren't able to source all the right equipment on-time.

Construction of the road is taking place in winter to minimize damage to the permafrost.